单项选择题

A generally accepted method to confirm accuracy of task progress is through ().

A.earned value
B.probability v outcome
C.maximum ceiling
D.work breakdown structure

<上一题 目录 下一题>
热门 试题

单项选择题
One common way to compute estimated at completion (EAC) is to take the project budgeted-at-completion and ().

A.divide it by the schedule performance index
B.multiply it by the schedule performance index
C.multiply it by the cost performance index
D.divide it by the cost performance index

单项选择题
A project's payback period ends when ().

A.profit maximum is realized
B.unit profit is realized
C.monthly revenue exceeds monthly costs
D.cumulative revenue equals cumulative costs