单项选择题

In your project, you have reason to believe that the current variances occurred because of extraneous factors, and you do not expect similar variances to happen in the future. What should be the estimate at complete for your project BAC=$300,000, AC=$100,000, EV=$150,000, CPI=$1.5 ?()

A.$250,000.
B.$220,000.
C.$280,000.
D.$200,000.

<上一题 目录 下一题>
热门 试题

单项选择题
Since you are in the preliminary stages of your project, you estimate that your project will most probably last 1 year-however, optimistic scenario is that it will get over within 6 months and pessimistic scenario is 18 months. This kind of estimate is also called ().

A.definitive
B.capital cost
C.order of magnitude
D.feasibility

单项选择题
Completion estimate (EAC) is the overall final value of a schedule activity, the WBS component, or the expected or planned project, when the project is defined. Which of the following information is required in order to compute EAC, assuming no management intervention is required ?()

A.to the current date of the EV and the actual cost of AC
B.cost performance index CPI and cost variable CV
C.to the current date of the actual cost of AC and the cost performance index CPI
D.the actual cost of AC and ETC to the current date