单项选择题

Since you are in the preliminary stages of your project, you estimate that your project will most probably last 1 year-however, optimistic scenario is that it will get over within 6 months and pessimistic scenario is 18 months. This kind of estimate is also called ().

A.definitive
B.capital cost
C.order of magnitude
D.feasibility