单项选择题

You have recently taken over a new project when the previous project manager resigned. While studying the project information, you find out that cost variances are very severe. To provide a realistic basis for performance measurement, you should recommend ().

A.issuing budget updates
B.revising the cost baseline
C.corrective action adjusting schedule activity budgets
D.closing the project