单项选择题

One common way to compute estimated at completion (EAC) is to take the project budgeted-at-completion and ().

A.divide it by the schedule performance index
B.multiply it by the schedule performance index
C.multiply it by the cost performance index
D.divide it by the cost performance index

<上一题 目录 下一题>
热门 试题

单项选择题
A project's payback period ends when ().

A.profit maximum is realized
B.unit profit is realized
C.monthly revenue exceeds monthly costs
D.cumulative revenue equals cumulative costs

单项选择题
While reviewing the estimates from the functional managers assigned to your project you discover that one cost estimate is clearly higher than those submitted for previous projects. You should ().

A.reject the estimate and remove the functional manager from the project
B.request the supporting details for the estimate to ensure it has been properly prepared
C.accept the estimate and plan to use the additional funding as a reserve
D.question each functional manager for information about this estimate

相关试题
  • During execution, a functional mana...
  • As a project manager, you are awa...
  • At XYZ Inc. , the hourly wage f...
  • You have recently taken over a new...
  • In your project, you have reason ...