单项选择题

Over the last few weeks, the team has made three scope changes to the activities and tasks on the projects. The project manager must be MOST careful to ______.

A. record all the changes
B. provide documentation on all the changes to the sponsor
C. make sure the changes are reflected in the project scope
D. prevent more changes from occurring