Two months into a design project, the customer requested a modification
to the project. The change was made a without notify the project manager. During
the final testing phase, result were different from what was planned for, This
scenario is an example of which of following
A. Poor definition of the test plan.
B. Poor development of quality management plan.
C. Poor use of scope change control.
D. Poor adherence to the communication plan.