A project manager is assigned to a new, high priority project. There are only five available resources because other resources are already committed to projects. The resource’s time available to complete the project is less than half the time needed, and the project manager cannot convince management to change the end date. The project manager should ______.

A. coordinate with team members the overtime necessary to complete the work
B. provide the team with opportunities to do a great job on the work that can be accomplished
C. cut the scope of work by removing the work that cannot be completed in the time provided
D. use more experienced resources to complete the work faster