If a project manager is told that modifying the scope of the project may provide added value for the customer, the project manager should ______.

A. change the WBS
B. change the scope baseline
C. fix a variance report
D. postpone the modification till a separate enhancement project in
<上一题 目录 下一题>
热门 试题

单项选择题
Two months into a design project, the customer requested a modification to the project. The change was made a without notify the project manager. During the final testing phase, result were different from what was planned for, This scenario is an example of which of following
A. Poor definition of the test plan.
B. Poor development of quality management plan.
C. Poor use of scope change control.
D. Poor adherence to the communication plan.
单项选择题
During a walk through of a task, you discover that a team member is completing the work differently than stated in the WBS directory. How should you deal with this
A. Tell the team member to take a corrective action.
B. Determine if the alternative way is acceptable to the functional manager.
C. Ask the team member if the changes are necessary.
D. Determine if the changes also change the scope of the work package.
相关试题
  • A project manager is assigned to a...
  • As a PM, you just received an on...
  • Because of a new government regulat...
  • A precise description of a delivera...
  • To integrate approved scope changes...