单项选择题

After preparing the probability distribution of cost outcome for a project, the estimate, with a 15% probability of being exceeded, is approximately one standard deviation ().

A.below the mean
B.above the median
C.above the mean
D.above the median

<上一题 目录 下一题>
热门 试题

单项选择题
The cost management plan has all of the following characteristics EXCEPT: ().

A.It is based on the project cost estimates, and is separate from the project pla
B.Can establish variance thresholds for costs or other indicator
C.May be formal or informal, highly detailed or broadly frame
D.Documents the cost management processes and their associated tools and technique

单项选择题
Given: BAC=200, AC=120, EV=80, CPI=0.666. Assuming that current variances are atypical, and that similar variances will not occur in the future, the estimate at completion (EAC) is ().

A.120
B.160
C.200
D.240

相关试题
  • During execution, a functional mana...
  • As a project manager, you are awa...
  • At XYZ Inc. , the hourly wage f...
  • You have recently taken over a new...
  • In your project, you have reason ...