单项选择题

Given: BAC=200, AC=120, EV=80, CPI=0.666. Assuming that current variances are atypical, and that similar variances will not occur in the future, the estimate at completion (EAC) is ().

A.120
B.160
C.200
D.240

<上一题 目录 下一题>
热门 试题

单项选择题
A recommended corrective action is an output of which cost management process area ?()

A.Resource plannin
B.Cost estimatin
C.Cost budgetin
D.Cost contro

单项选择题
In your construction project, the CPI is 1.30 and SPI is 0.85. What could be the potential reason ?()

A.A critical resource went on sick leave for a long period of time, which had not been anticipated earlie
B.The Cost of raw materials required for construction increased 10%.
C.You had not taken into account inflation rat
D.There was 4 days waiting time in the curing of cement, and work could not be done during that tim

相关试题
  • During execution, a functional mana...
  • As a project manager, you are awa...
  • At XYZ Inc. , the hourly wage f...
  • You have recently taken over a new...
  • In your project, you have reason ...