单项选择题

To define variance thresholds at designated time points over the duration of a project, you will use ().

A.units of measure
B.precision level
C.organizational procedure links
D.control thresholds

<上一题 目录 下一题>
热门 试题

单项选择题
Which of the following choices indicates that your project is 9% under budget ?()

A.The cumulative AC was 100, and the cumulative EV was 110
B.The cumulative PV was 100, and the cumulative AC was 110
C.The cumulative AC was 110, and the cumulative EV was 100
D.The cumulative EV was 100, and the cumulative PV was 110

单项选择题
Cost control outputs include all of the following EXCEPT ().

A.estimate at completion
B.budget updates
C.revised cost estimates
D.cost baseline