单项选择题

A projeet team budgeted US $3,000 for the work performed and has spent US $4,000 to date. If they budgeted US $5, 000 for the work scheduled, what is the cost variance

A) $-1,000.
B) $2,000.
C) $1,000.
D) $-2,000.
<上一题 目录 下一题>
热门 试题

单项选择题
Including a contingency reserve in the project budget is intended to ______ .
A) reduce the probability of scope changes
B) increase the probability of scope changes
C) reduce the probability of a cost overrun
D) increase the probability of a cost overrun
单项选择题
Which of the following choices indicates that your project is 9% under budget
A) The cumulative AC was 100, and the cumulative EV was 110.
B) The cumulative PV was 100, and the cumulative AC was 110.
C) The cumulative AC was 110, and the cumulative EV was 100.
D) The cumulative EV was 100, and the cumulative PV was 110.
相关试题
  • In your project, there have been ...
  • One common way to compute estimated...
  • The cost reserve should be ____...
  • During execution, a functional mana...
  • The estimate at completion (EAC) ...