单项选择题

Which of the following choices indicates that your project is 9% under budget

A) The cumulative AC was 100, and the cumulative EV was 110.
B) The cumulative PV was 100, and the cumulative AC was 110.
C) The cumulative AC was 110, and the cumulative EV was 100.
D) The cumulative EV was 100, and the cumulative PV was 110.
<上一题 目录 下一题>
热门 试题

单项选择题
Since you are in the preliminary stages of your project, you estimate that your project will most probably last 1 year-however, optimistic scenario is that it will get over within 6 months and pessimistic scenario is 18 months. This kind of estimate is also called ______ .
A) definitive
B) capital cost
C) order of magnitude
D) feasibility
单项选择题
At XYZ Inc. , the hourly wage for semi-skilled workers is $14.00. The annual audit shows that fringe benefits cost 30%of basic wages, and that overhead costs are 60% of wages plus fringe benefits. What is the “loaded” hourly wage for a semi-skilled worker at XYZ Inc.
A) $27.14.
B) $28.96.
C) $30.03.
D) $29.12.
相关试题
  • In your project, there have been ...
  • One common way to compute estimated...
  • The cost reserve should be ____...
  • During execution, a functional mana...
  • The estimate at completion (EAC) ...