单项选择题

Including a contingency reserve in the project budget is intended to ______ .

A) reduce the probability of scope changes
B) increase the probability of scope changes
C) reduce the probability of a cost overrun
D) increase the probability of a cost overrun
<上一题 目录 下一题>
热门 试题

单项选择题
Which of the following choices indicates that your project is 9% under budget
A) The cumulative AC was 100, and the cumulative EV was 110.
B) The cumulative PV was 100, and the cumulative AC was 110.
C) The cumulative AC was 110, and the cumulative EV was 100.
D) The cumulative EV was 100, and the cumulative PV was 110.
单项选择题
Since you are in the preliminary stages of your project, you estimate that your project will most probably last 1 year-however, optimistic scenario is that it will get over within 6 months and pessimistic scenario is 18 months. This kind of estimate is also called ______ .
A) definitive
B) capital cost
C) order of magnitude
D) feasibility
相关试题
  • In your project, there have been ...
  • One common way to compute estimated...
  • The cost reserve should be ____...
  • During execution, a functional mana...
  • The estimate at completion (EAC) ...