At XYZ Inc. , the hourly wage for semi-skilled workers is $14.00. The annual audit shows that fringe benefits cost 30%of basic wages, and that overhead costs are 60% of wages plus fringe benefits. What is the “loaded” hourly wage for a semi-skilled worker at XYZ Inc.

A) $27.14.
B) $28.96.
C) $30.03.
D) $29.12.
<上一题 目录 下一题>
热门 试题

单项选择题
In your project, you have reason to believe that the current variances occurred because of extraneous factors, and you do not expect similar variances to happen in the future. What should be the estimate at complete for your project BAC=$300,000, AC=$100,000, EV=$150,000, CPI=$1.5.
A) $250,000.
B) $220,000.
C) $280,000.
D) $200,000.
单项选择题
Earned value technique(EVT)is a tool and technique to measure project performance. In EVT, BCWP refers to ______ .
A) physical work actually accomplished, including the estimated value of this work
B) physical work scheduled to be performed, including the estimated value of this work
C) actual cost incurred to accomplish the earned value
D) none of the above
相关试题
  • In your project, there have been ...
  • One common way to compute estimated...
  • The cost reserve should be ____...
  • During execution, a functional mana...
  • The estimate at completion (EAC) ...