单项选择题

In your project, you have reason to believe that the current variances occurred because of extraneous factors, and you do not expect similar variances to happen in the future. What should be the estimate at complete for your project BAC=$300,000, AC=$100,000, EV=$150,000, CPI=$1.5.

A) $250,000.
B) $220,000.
C) $280,000.
D) $200,000.
<上一题 目录 下一题>
热门 试题

单项选择题
Earned value technique(EVT)is a tool and technique to measure project performance. In EVT, BCWP refers to ______ .
A) physical work actually accomplished, including the estimated value of this work
B) physical work scheduled to be performed, including the estimated value of this work
C) actual cost incurred to accomplish the earned value
D) none of the above
单项选择题
You are getting project performance information as your project is being executed. Based on the performance information, forecasts are updated and reissued. Some factors that could change as forecasts are updated include ______ .
A) estimate to complete
B) estimate at completion
C) estimate to complete and estimate at completion
D) none of the above
相关试题
  • In your project, there have been ...
  • One common way to compute estimated...
  • The cost reserve should be ____...
  • During execution, a functional mana...
  • The estimate at completion (EAC) ...