When should a project baseline be changed

A) When a major delay occurs.
B) When an official change is made.
C) When a cost increase occurs.
D) Changes should never be made in the baseline.
<上一题 目录 下一题>
热门 试题

单项选择题
All of the following are part of an effective change control system EXCEPT
A) procedures
B) standards for reports
C) meetings
D) lessons learned
单项选择题
While the project is being completed, management requests a change. What is the FIRST thing the project manager should do
A) Comply with the request if possible.
B) Obtain a complete understanding of the scope of the change.
C) Teel the customer that a change will be coming.
D) Ask the team to accept the change.