单项选择题
Administrative closure should not be delayed until project completion because
A) useful information may be lost
B) the project manager may be reassigned
C) project team members may be reassigned by that time
D) sellers are anxious for payments
点击查看答案&解析
<上一题
目录
下一题>
热门
试题
单项选择题
Which two process groups provide potentially cyclical inputs to each other
A) Executing processes and controlling processes.
B) Planning processes and executing processes.
C) Planning processes and controlling processes.
D) Controlling processes and closing processes.
点击查看答案&解析
单项选择题
An important task of project managers is to identify the relevant goals of each project. An approach that can help managers set up and achieve those goals is management by objectives (MBO). MBO specifically addresses all the following EXCEPT ______.
A) establishing unambiguous and realistic objectives
B) periodically evaluating whether project objectives have been achieved
C) promoting participation, team building, and commitment to the project
D) analyzing and reducing risk and determining how to handle it when it occurs
点击查看答案&解析