单项选择题

All of the following are part of an effective change control system EXCEPT

A) procedures
B) standards for reports
C) meetings
D) lessons learned
<上一题 目录 下一题>
热门 试题

单项选择题
While the project is being completed, management requests a change. What is the FIRST thing the project manager should do
A) Comply with the request if possible.
B) Obtain a complete understanding of the scope of the change.
C) Teel the customer that a change will be coming.
D) Ask the team to accept the change.
单项选择题
Which of the followings is far from Integrated Change Control
A) Influencing the factors that create change to ensure that changes are agreed upon.
B) Determining that a change has occurred.
C) Ensuring the integrated performance baseline doesn't change.
D) Managing the actual changes when and as they occur.
相关试题
  • The close project or phase process...
  • In which project life cycle phase ...
  • A project planning methodology is a...
  • The competitive, complex project ma...
  • Administrative closure should not be...