单项选择题

Which of the following tool is used for scope verification

A.Performance measuremen
B.Scope change control syste
C.Inspectio
D.Earned valu
<上一题 目录 下一题>
热门 试题

单项选择题
All of the following assist in determining the impact of a scope change EXCEPT______.
A.project charter
B.baseline
C.performance measurement
D.milestones
单项选择题
An example of scope verification is ______ .
A.review the performance of an installed software module
B.managing changes to the project schedule
C.decomposing the WBS to a work package level
D.performing a benefit/cost analysis to determine if we should proceed with the project