单项选择题

All of the following assist in determining the impact of a scope change EXCEPT______.

A.project charter
B.baseline
C.performance measurement
D.milestones
<上一题 目录 下一题>
热门 试题

单项选择题
An example of scope verification is ______ .
A.review the performance of an installed software module
B.managing changes to the project schedule
C.decomposing the WBS to a work package level
D.performing a benefit/cost analysis to determine if we should proceed with the project
单项选择题
Scope change control MUST be integrated with all of the following control processes EXCEPT ______ .
A.schedule
B.cost
C.procurement
D.quality
相关试题
  • The owner (buyer)of a project usu...
  • You are the project manager for an...
  • The former head of your project of...
  • The U.S. Bureau of Indian Affairs...
  • Your project involves manufacturing ...