单项选择题

The measure used to forecast project cost at completion is ().

A.CPI
B.SPI
C.BCWP
D.ACWP

<上一题 目录 下一题>
热门 试题

单项选择题
Earned value technique(EVT)is a tool and technique to measure project performance. In EVT, BCWP refers to ().

A.physical work actually accomplished, including the estimated value of this work
B.physical work scheduled to be performed, including the estimated value of this work
C.actual cost incurred to accomplish the earned value
D.none of the above

单项选择题
Of the following estimates, which most accurately reflect the actual cost of the project ?()

A.Conceptual estimate
B.Order of magnitude estimate
C.Preliminary estimate
D.Bottom-up estimat