During the project scope planning process, the work breakdown structure should be developed to ______ .

A) the sub-project level
B) the level determined by the project office
C) a level allowing for adequate estimates
D) the cost center level
<上一题 目录 下一题>
热门 试题

单项选择题
A scope statement is important because it ______ .
A) provides the basis for making future project decisions
B) provides a brief summary of the project
C) approves the project for the stakeholders
D) provides criteria for measuring project cost
单项选择题
Due to cuts in funding, your project has been terminated. The scope verification process ______ .
A) should be delayed until the project is completed
B) should determine the correctness of the work results
C) should establish and document the level and extent of completion
D) will form the basis of the project audit