A scope statement is important because it ______ .
A) provides the basis for making future project decisions
B) provides a brief summary of the project
C) approves the project for the stakeholders
D) provides criteria for measuring project cost
点击查看答案&解析
<上一题
目录
下一题>
热门
试题
单项选择题
Due to cuts in funding, your project has been terminated. The scope verification process ______ .
A) should be delayed until the project is completed
B) should determine the correctness of the work results
C) should establish and document the level and extent of completion
D) will form the basis of the project audit
点击查看答案&解析
单项选择题
The U.S. Bureau of Indian Affairs awarded your firm a contact to renovate an elementary school on a Navajo reservation. One contractual term, Indian preference, requires you to hire native American Laborers and subcontractors from the reservation. This is an example of which type of the following constraints
A) Social.
B) Economical.
C) Environmental.
D) Legal.