单项选择题

A project manager believes that modifying the project scope may provide added value for the customer. What should the project manager do

A) Change the scope baseline.
B) Contact the customer to determine if the change adds value.
C) Call a meeting of the change control board.
D) Change the project’s objectives.
<上一题 目录 下一题>
热门 试题

单项选择题
The purpose of the scope statement includes all but which of the following:
A) Provides a basis for future project decisions.
B) Establishes a contract between the project team and the customer.
C) Sets criteria to use to determine if a project or phase have been completed successfully.
D) Establishes project constraints and assumptions.
单项选择题
Scope planning for a project is ______ .
A) the project specification that includes design principles and project objectives
B) a three-level project work breakdown structure
C) the process of creating a project scope management plan
D) the record showing that all project deliverables are completed satisfactorily
相关试题
  • Reviewing work products and results...
  • The former head of your project of...
  • The decomposition process is a tech...
  • An output of scope definition is ...
  • A precision description of a delive...