单项选择题

Reviewing work products and results to ensure that all were completed satisfactorily and formally accepted is part of ______ .

A) risk management
B) quality control
C) change control management
D) verify scope
<上一题 目录 下一题>
热门 试题

单项选择题
You are the project manager for an initiative aimed at releasing a new product in the market. But because of government regulation, you will have to make some changes to the project scope and the WBS. Any approved modifications to the contents of the scope statement should be done through ______ updates.
A) scope management plan
B) work breakdown structure
C) project plan
D) none of the above
单项选择题
A work breakdown structure (WBS) numbering system should allow project staff to ______ .
A) identify the level at which individual WBS elements are found
B) identify configuration management milestones
C) estimate the costs of WBS elements
D) provide project justification