单项选择题

A work breakdown structure (WBS) numbering system should allow project staff to ______ .

A) identify the level at which individual WBS elements are found
B) identify configuration management milestones
C) estimate the costs of WBS elements
D) provide project justification
<上一题 目录 下一题>
热门 试题

单项选择题
The work breakdown structure is an excellent tool for objective control and evaluation. Which of the following is generally not validated through the WBS
A) Time, schedule, and cost.
B) Management coordination and organizational structuring.
C) Risk and impact of decision—making.
D) Quality of the work.
单项选择题
A code of accounts ______ .
A) is any numbering system used to uniquely identify each component of the work breakdown structure
B) includes work packages, used to track phase completion
C) is an organizational scheme to keep track of contracts
D) charts elements of the WBS against the timeline