单项选择题

A code of accounts ______ .

A) is any numbering system used to uniquely identify each component of the work breakdown structure
B) includes work packages, used to track phase completion
C) is an organizational scheme to keep track of contracts
D) charts elements of the WBS against the timeline
<上一题 目录 下一题>
热门 试题

单项选择题
What may the project team do to confirm the scope of the project is on track
A) Review change requests that have been submitted and approved.
B) Obtain status from responsible individuals on the team.
C) Conduct walkthrough, inspections and reviews.
D) Complete a scope report and submit it to management.
单项选择题
Which of the following is true about the WBS:
A) The WBS is another term for the Gantt chart.
B) Each descending level of the WBS represents an increasingly detailed definition of the project work.
C) Work not in the WBS is usually defined in the scope statement of the project.
D) The WBS shows only the critical path activities.