单项选择题
The connection between two networks to form an internet is handled by a machine known as a ______.
A.bridge
B.client
C.router
D.switch
点击查看答案
<上一题
目录
下一题>
热门
试题
单项选择题
______ is one of the techniques used for estimating activity durations.
A.Analogous Estimating
B.Precedence Diagramming Method (PDM)
C.Dependency Determination
D.Schedule network Templates
点击查看答案
单项选择题
Project Time Management includes the processes required to manage timely completion of the project, these processes interact with each other. ______ is following the process - Estimate Activity Durations.
A.Develop Schedule
B.Estimate Activity Resources
C.Define Activities
D.Sequence Activities
点击查看答案
相关试题
Which statement about the preliminar...
Tool for defining activities is _...
You are a project manager for a s...
10BaseT is an Ethernet LAN term ...
Sub-contractors should obey the con...