单项选择题
Tool for defining activities is ______.
A.Dependency Determination
B.Precedence Diagramming method
C.Rolling Wave Planning
D.Schedule network Templates
点击查看答案
<上一题
目录
下一题>
热门
试题
单项选择题
You are a project manager for a small project. Your project was budgeted for ¥500,000 over a six-week perioD. As of today, you’ve spent ¥260,000 of your budget to complete work that you originally expected to cost ¥280,000. According to your schedule, you should have spent ¥300,000 by this point. Based on these circumstances, your project could be BEST described as ______
A.Ahead of schedule
B.Behind schedule
C.On schedule
D.Having not enough information provided
点击查看答案
单项选择题
10BaseT is an Ethernet LAN term meaning a maximum transfer rate of 10Mbps that uses baseband signaling and twisted pair cabling. A 10BaseT Ethernet LAN has a ______ topology.
A.star
B.ring
C.bus
D.none of the above
点击查看答案
相关试题
Which statement about the preliminar...