单项选择题
______ is one of the techniques used for estimating activity durations.
A.Analogous Estimating
B.Precedence Diagramming Method (PDM)
C.Dependency Determination
D.Schedule network Templates
点击查看答案
<上一题
目录
下一题>
热门
试题
单项选择题
Project Time Management includes the processes required to manage timely completion of the project, these processes interact with each other. ______ is following the process - Estimate Activity Durations.
A.Develop Schedule
B.Estimate Activity Resources
C.Define Activities
D.Sequence Activities
点击查看答案
单项选择题
A.executeB.interpretC.compileD.maintain
A.execute
B.interpret
C.compile
D.maintain
点击查看答案&解析