Generally accepted methods for translating project objectives into tangible deliverables and requirements is also referred to as ______ .

A) product analysis
B) risk measurement
C) alternatives identification
D) benefit/cost analysis
<上一题 目录 下一题>
热门 试题

单项选择题
An example of scope verification is ______ .
A) review the performance of an installed software module
B) managing changes to the project schedule
C) decomposing the WBS to a work package level
D) performing a benefit/cost analysis to determine if we should proceed with the project
单项选择题
As a project manager, the most important activity to ensure customer and stakeholder satisfaction is ______ .
A) documenting the performance measurements
B) reporting changes and updating the project plan and other project documents where appropriate
C) reporting project status timely and regularly
D) documenting the requirements