单项选择题
An example of scope verification is ______ .
A) review the performance of an installed software module
B) managing changes to the project schedule
C) decomposing the WBS to a work package level
D) performing a benefit/cost analysis to determine if we should proceed with the project
点击查看答案&解析
<上一题
目录
下一题>
热门
试题
单项选择题
As a project manager, the most important activity to ensure customer and stakeholder satisfaction is ______ .
A) documenting the performance measurements
B) reporting changes and updating the project plan and other project documents where appropriate
C) reporting project status timely and regularly
D) documenting the requirements
点击查看答案&解析
单项选择题
In your project, you use product analysis to translating project objectives into tangible deliverables and requirements. All the following tools are used for product analysis EXCEPT ______ .
A) value engineering
B) value analysis
C) product breakdown
D) benefit/cost analysis
点击查看答案&解析