单项选择题

The () is a time-phased budget that will be used to measure and monitor cost performance in the project.

A.work breakdown structure
B.project schedule
C.cost baseline
D.cost budget

<上一题 目录 下一题>
热门 试题

单项选择题
The cost baseline has all of the following characteristics EXCEPT: ().

A.It is a time-phased budget that will be used to measure and monitor cost performance on the projec
B.It shows the actual cost expenditures throughout the life of the projec
C.It is developed by summing estimated costs by perio
D.It is usually displayed in the form of an S-curv

单项选择题
A project was expected to cost $6 million for 3 months. At the end of 1 month, you use earned value as a performance management tool and get the following information: BCWP=$1.5 million, BCWS=$2.5 million, ACWP=$2.2.million. What is the schedule variance ?()

A.$0.3 millio
B.$-1 millio
C.$1 million。
D.$0.7 millio

相关试题
  • During execution, a functional mana...
  • As a project manager, you are awa...
  • At XYZ Inc. , the hourly wage f...
  • You have recently taken over a new...
  • In your project, you have reason ...