单项选择题
A.reduce the probability of scope changes B.increase the probability of scope changes C.reduce the probability of a cost overrun D.increase the probability of a cost overrun
A.$-1,000. B.$2,000. C.$1,000. D.$-2,000.
A.CVs are severe, and a realistic measure of performance is needed B.revised cost estimates are prepared and distributed to stakeholders C.corrective action must be taken to bring expected future performance in line with the project plan D.EAC shows that additional funds are needed to complete the project even if a scope change is not needed