单项选择题

In the earned value technique, cost variance is computed as ().

A.EV minus PV
B.EV minus AC
C.AC minus EV
D.PV minus EV

<上一题 目录 下一题>
热门 试题

单项选择题
Your company has established a reward and recognition system for its project management professionals. Project cost performance is used as a criterion to determine rewards. What should you do to ensure that rewards reflect actual performance ?()

A.Consider overtime work as part of the jo
B.Prepare a cost baselin
C.Use earned value management to monitor performanc
D.Estimate and budget controllable and uncontrollable costs separatel

单项选择题
Earned value technique(EVT)can best be defined as ().

A.analysis of the value of the equipment that has been installed as of the date
B.analysis of the sum of the labor costs, which have been incurred on the project to date
C.a method of project performance measurement
D.a method of measuring the amount of money that has been spent to date

相关试题
  • During execution, a functional mana...
  • As a project manager, you are awa...
  • At XYZ Inc. , the hourly wage f...
  • You have recently taken over a new...
  • In your project, you have reason ...