单项选择题

Who is responsive for determining the project cost variance acceptable range ?()

A.Functional manage
B.Upper managemen
C.The custome
D.The project manage

<上一题 目录 下一题>
热门 试题

单项选择题
A project manager needs to analyze the project cost to find ways to decrease costs. It would be BEST if the project manager looks at ().

A.variable costs and fixed costs
B.fixed costs and indirect cost
C.direct costs and variable costs
D.indirect costs and direct costs

单项选择题
All of the following are examples of tools often used in estimate costs EXCEPT ().

A.parametric modeling
B.analogous estimating
C.bottom-up estimating
D.activity duration estimates