单项选择题

Being assigned as the project manager to a project you perform earned value Analysis and find the following results:EV=250000;PV=200000;AC=275000;BAC=500000.What is right ?()

A.EAC=400000
B.EAC=550000
C.BTC=400000
D.ETC=75000