单项选择题
In your project,you have identified list of identified risks,list of potential responses and root causes of risks.You should document this information in the______.
A.risk management plan
B.risk database
C.project plan
D.risk register
点击查看答案&解析
<上一题
目录
下一题>
热门
试题
单项选择题
Workaround is______.
A.a response to a negative risk that has occurreA workaround is not planned in advance of the occurrence of the risk event
B.a contingency plan
C.implementation of the contingency plan for a positive risk event
D.using global sourcing to continue project development around the clock
点击查看答案&解析
单项选择题
You are in the build phase of the project.But it has run into several unanticipated problems.Several risks have surfaced which you had not anticipated earlier.The project is over-budget and behind schedule.What should you do
A.Create updates to risk response pla
B.Create a revised project pla
C.Perform risk response audit
D.Perform updated risk identification and analysi
点击查看答案&解析