单项选择题

Workaround is______.

A.a response to a negative risk that has occurreA workaround is not planned in advance of the occurrence of the risk event
B.a contingency plan
C.implementation of the contingency plan for a positive risk event
D.using global sourcing to continue project development around the clock
<上一题 目录 下一题>
热门 试题

单项选择题
You are in the build phase of the project.But it has run into several unanticipated problems.Several risks have surfaced which you had not anticipated earlier.The project is over-budget and behind schedule.What should you do
A.Create updates to risk response pla
B.Create a revised project pla
C.Perform risk response audit
D.Perform updated risk identification and analysi
单项选择题
The major processes of risk management are______.
A.planning,identification,documentation,and assessment
B.identification,planning,evaluation,response development,mitigation,and documentation
C.identification,response development,assessment,and documentation
D.planning,identification,qualitative analysis,quantitative analysis,response planning,and monitoring and control
相关试题
  • The probability of failure for a p...
  • You are beginning a new project th...
  • You had budgeted $200000 in ...
  • In your project,you have identifed...
  • You are the project manager in an...