单项选择题

when is the greatest difference between risks or opportunities and investment at stake

A.Conceptio
B.Developmen
C.Implementatio
D.Closur
<上一题 目录 下一题>
热门 试题

单项选择题
In your project,you have identified list of identified risks,list of potential responses and root causes of risks.You should document this information in the______.
A.risk management plan
B.risk database
C.project plan
D.risk register
单项选择题
Workaround is______.
A.a response to a negative risk that has occurreA workaround is not planned in advance of the occurrence of the risk event
B.a contingency plan
C.implementation of the contingency plan for a positive risk event
D.using global sourcing to continue project development around the clock