单项选择题

Rearranging resources so that constant resource levels are maintained is called ______ .

A.floating
B.leveling
C.restructuring
D.crashing
<上一题 目录 下一题>
热门 试题

单项选择题
The “three-point estimates” method for estimating activity duration differs from the “single point, most-likely estimate” method in that it uses ______ .
A.an average of the three estimated durations to estimate activity duration
B.“dummy” activities to represent logic ties
C.“free float” instead of “total float” in the schedule calculations
D.bar charts instead of logic diagrams to portray the schedule
单项选择题
In your project, some requested changes were generated from the activity definition process. These changes will be processed through ______ .
A.activity change control system
B.corrective action
C.integrated change control system
D.activity sequencing
相关试题
  • You work for one of the leading m...
  • You are doing a Monte Carlo Analys...
  • Resource calendars affect a specific...
  • You work for an architectural-engin...
  • You have taken information on proje...