单项选择题

In your project, some requested changes were generated from the activity definition process. These changes will be processed through ______ .

A.activity change control system
B.corrective action
C.integrated change control system
D.activity sequencing
<上一题 目录 下一题>
热门 试题

单项选择题
As one of the tools and techniques of activity sequencing, a lead ______ .
A.directs a delay in the successor activity
B.could be accomplished by a finish to-start relationship with a delay time
C.means the successor activity cannot start until after the predecessor is completed
D.allows an acceleration of the successor activity
单项选择题
Analogous duration estimating is ______ .
A.bottom-up estimating
B.frequently used to estimate project duration when there is a limited amount of detailed information
C.similar to multiple duration estimating
D.deductive estimating
相关试题
  • You work for one of the leading m...
  • You are doing a Monte Carlo Analys...
  • Resource calendars affect a specific...
  • You work for an architectural-engin...
  • You have taken information on proje...