单项选择题

An activity has an optimistic estimate of 10 days, pessimistic estimate of 16 days, most likely estimate of 13 days. Assuming a normal distribution, what is the probability that the task will be completed within 10~16 days

A.99.99%.
B.99.73 Y0.
C.95.46%.
D.68.26%.
<上一题 目录 下一题>
热门 试题

单项选择题
The hybrid of a project network diagram and bar chart is called ______ .
A.time-scaled network diagram
B.gantt chart
C.AON
D.precedence diagramming method
单项选择题
The project time management processes include ______ .
A.define activities, sequence activities, estimate activity resources, and estimate activity durations
B.define activities, activity sequencing, and activity duration estimating
C.activity identification, activity execution, and activity results
D.activity determination, activity duration estimating, activity implementation, and activity results
相关试题
  • You work for one of the leading m...
  • You are doing a Monte Carlo Analys...
  • Resource calendars affect a specific...
  • You work for an architectural-engin...
  • You have taken information on proje...