单项选择题

The hybrid of a project network diagram and bar chart is called ______ .

A.time-scaled network diagram
B.gantt chart
C.AON
D.precedence diagramming method
<上一题 目录 下一题>
热门 试题

单项选择题
The project time management processes include ______ .
A.define activities, sequence activities, estimate activity resources, and estimate activity durations
B.define activities, activity sequencing, and activity duration estimating
C.activity identification, activity execution, and activity results
D.activity determination, activity duration estimating, activity implementation, and activity results
单项选择题
A planning package is a ______ .
A.unit of the project plan
B.unit of the scope management plan
C.WBS component below the control account
D.template used for the project