单项选择题
All of the following assist in determining the impact of a scope change EXCEPT______.
A) project charter
B) baseline
C) performance measurement
D) milestones
点击查看答案&解析
<上一题
目录
下一题>
热门
试题
单项选择题
Completion of project scope activities is not measured against the ______ .
A) scope statement
B) requirements
C) WBS dictionary
D) WBS
点击查看答案&解析
单项选择题
The decomposition process is a technique used to construct a ______ .
A) precedence network
B) critical path method diagram
C) variance analysis
D) work breakdown structure
点击查看答案&解析