单项选择题

A response to a risk that was not defined in advance of its occurrence is called a______.

A.risk mitigation response
B.workaround response
C.corrective action response
D.contingency response
<上一题 目录 下一题>
热门 试题

单项选择题
The most crucial time for project risk assessment is______.
A.when a problem surfaces
B.during the planning phase
C.during the close-out phase
D.after the project schedule has been published
单项选择题
To be successful,the organization should be committed to addressing the management of risk______.
A.just before a meeting with a client
B.proactively and consistently throughout the project
C.as soon as time and cost estimates are ready
D.early in the execution phase