单项选择题
The most crucial time for project risk assessment is______.
A.when a problem surfaces
B.during the planning phase
C.during the close-out phase
D.after the project schedule has been published
点击查看答案&解析
<上一题
目录
下一题>
热门
试题
单项选择题
To be successful,the organization should be committed to addressing the management of risk______.
A.just before a meeting with a client
B.proactively and consistently throughout the project
C.as soon as time and cost estimates are ready
D.early in the execution phase
点击查看答案&解析
单项选择题
Risk identification outputs include the following except______.
A.decision trees
B.inputs to other processes
C.risk symptoms
D.potential risk events
点击查看答案&解析