单项选择题
During the project scope planning process, the work breakdown structure should be developed to ______ .
A.the sub-project level
B.the level determined by the project office
C.a level allowing for adequate estimates
D.the cost center level
点击查看答案&解析
<上一题
目录
下一题>
热门
试题
单项选择题
A KEY activity for achieving customer satisfaction is to define ______ .
A.the business use
B.requirements
C.product specificity
D.change control
点击查看答案&解析
单项选择题
Due to cuts in funding, your project has been terminated. The scope verification process ______ .
A.should be delayed until the project is completed
B.should determine the correctness of the work results
C.should establish and document the level and extent of completion
D.will form the basis of the project audit
点击查看答案&解析